“World-Class Economy, Third-World Service
|
🎧--- Listen To This Article Here : 👇🏽
|
592GUARDIAN♦ACCOUNTABILITY♦GRITY IN JOURNALISM♦GUYANA
“World-Class Economy, Third-World Service: Guyana Cannot Keep Apologising for Darkness”
OPINION BY :Hem Kumar November 2026
Part II: From apologies to enforceable action
President Irfaan Ali’s promise to investigate the 45-hour East Berbice-Corentyne blackout is necessary, but it cannot be the end of the matter. Guyanese do not need another report that identifies a technical fault, expresses regret and disappears into a government archive.
They need enforceable standards, automatic compensation, resilient infrastructure and accountability that reaches the people with authority to prevent failure.
The Canefield Substation fault was traced to an insulation failure in a grounding-transformer panel, with GPL replacing defective components before beginning incremental restoration. But the deeper question remains: why was a single failure able to leave an entire region without electricity for more than two days—and why did it also compromise water supply at several GWI facilities?
Automatic compensation for outages
Guyana should establish an Essential Services Consumer Guarantee requiring automatic compensation for prolonged electricity outages. Consumers should not have to file complaints, hire lawyers or beg for credits after enduring a systemic failure.
A practical standard would be:
- 12 to 23 hours without electricity: automatic credit equal to one day’s basic electricity charge.
- 24 to 47 hours: automatic credit equal to three days’ basic electricity charge.
- 48 hours or more: automatic credit equal to seven days’ basic electricity charge, plus an additional daily credit for every further 24-hour period.
- Three or more qualifying outages within 90 days: escalating compensation and a mandatory PUC investigation.
The United Kingdom already operates a comparable principle through Ofgem’s Guaranteed Standards, under which network operators must make automatic payments when supply is interrupted beyond specified thresholds. Guyana need not copy every detail, but it should adopt the principle: prolonged failure by an essential monopoly service must carry a financial consequence.
There is local precedent. The Public Utilities Commission has recorded credits granted to consumers after service-standard breaches, and GPL has previously been required to credit customer accounts within 30 days for breaches of its Customer Service Standards. What is needed now is a system-wide, automatic remedy—not a complaint-by-complaint process that leaves the most vulnerable consumers behind.
Compensation for businesses
Households are not the only victims. Shops, pharmacies, restaurants, manufacturers, farms, service providers and other businesses suffer real losses when power fails for days. They lose perishable stock, production time, customers, equipment and income.
Guyana should create a Business Continuity Claims Scheme for documented losses arising from outages lasting 24 hours or more. Eligible claims should include spoiled inventory, generator fuel and reasonable hire costs, damage to refrigeration or machinery, emergency lighting and security costs, and verified lost revenue.
Claims should be decided within 30 days, with a right of appeal to the PUC. This is not a handout; it is a fair allocation of risk. GPL and the state benefit from the revenue and taxes generated by businesses, so they must also ensure that businesses are not left to carry the full cost of infrastructure failure.
A 12-hour restoration guarantee
GPL should be required to restore supply, provide an alternative supply, or publish a credible restoration plan within 12 hours of a major outage. After that point, it must provide public updates at least every four hours.
Those updates should state the affected communities, technical cause, estimated restoration time, customers and critical facilities still without service, any load-shedding arrangements, and emergency water-distribution measures where necessary.
A 45-hour blackout should automatically trigger a PUC investigation and a public report within 30 days. The report must identify the cause, the decisions taken, the cost of the failure, the customers affected, compensation paid and the corrective actions required.
Make the grid resilient
GPL must conduct and publish a nationwide Resilience Audit within 90 days. The audit should identify ageing switchgear, transformers, panels, cables and protection systems; single points of failure capable of blacking out an entire region; missing spare parts; deferred maintenance; staffing gaps; and the need for mobile generators, temporary substations or redundant feeders.
The audit must be followed by a costed remediation plan, with quarterly public reporting on progress. Citizens should be able to see which communities remain vulnerable, which projects are delayed, and which risks have been addressed.
This is especially important as Guyana invests heavily in energy infrastructure. The Gas-to-Energy project and other major investments may improve generation capacity, but they will not solve distribution failures, poor maintenance, absent spares or weak emergency planning unless those problems are directly addressed.
Water cannot wait for power
The blackout exposed a second systemic weakness: GWI’s dependence on grid electricity at critical facilities. GWI advised that the Edinburg, Cumberland, Lochaber, Adventure and Manchester well stations were affected by power failures. That means a failure in one utility cascaded directly into another essential service.
GWI must be required to achieve backup-power readiness at every critical well station and treatment plant within 12 months. Each facility should have:
- A tested standby generator sized for essential pumping and treatment loads.
- Automatic transfer switching, or a documented rapid manual-changeover protocol.
- At least 72 hours of fuel reserves and a standing fuel-delivery arrangement.
- Monthly load-testing and preventive-maintenance records.
- A water-security plan for prolonged outages, including emergency distribution where needed.
- Solar-plus-battery storage or other off-grid capability where feasible.
GWI should publish a facility-by-facility resilience scorecard. A well station without dependable backup power should be treated as a priority capital project, not an acceptable operational gap.
Use the PUC’s authority
The Public Utilities Commission is not merely a complaint office. Its mandate includes ensuring that utilities deliver services meeting statutory standards, monitoring service quality, investigating providers and imposing penalties for breaches.
The PUC should therefore review and update GPL’s Operating Standards and Performance Targets, and enforce them without hesitation. Its orders already establish that GPL’s operating standards and performance targets constitute the quality of service GPL is required to provide.
Where GPL repeatedly or severely breaches those standards, the PUC should apply monetary penalties. Its existing framework provides for penalties of up to 25% of dividends payable to GPL’s shareholder in a calendar year. Penalty revenue should be transparently directed to consumer compensation, network resilience or a documented essential-services improvement fund.
Investigate upward, not downward
The Canefield investigation must be independent, public and comprehensive. It should examine not only the failed component, but the decisions that allowed the failure to become a 45-hour regional crisis.
It must ask whether maintenance was adequate, whether spare parts were available, whether warnings or prior incidents were ignored, whether capital works were delayed, whether procurement was efficient, and whether GPL’s board, management and relevant ministries exercised proper oversight.
It must also examine GWI’s contingency arrangements. If critical water facilities had no functioning backup power, no fuel reserve, no rapid changeover capability or no emergency plan, the public deserves to know who was responsible.
Accountability cannot mean charging or disciplining a technician while those who approved budgets, deferred maintenance, ignored risks or failed to plan for redundancy remain untouched. Responsibility must follow authority.
Publish the facts
GPL and GWI should jointly publish a monthly Essential Services Reliability Report. It should disclose the number and duration of outages, communities affected, causes, restoration times, water interruptions caused by power failures, compensation paid, capital projects completed or delayed, and PUC enforcement actions.
Transparency is not a punishment for the utilities. It is the minimum condition for public trust. Citizens cannot assess whether billions are being spent wisely if they cannot see whether service is improving.
The demand
Guyana does not lack the legal tools, institutional authority or financial resources to prevent a repeat of this crisis. What it needs is the political will to convert promises into enforceable obligations.
The government should commit to:
- Automatic consumer compensation for prolonged outages.
- A fair claims process for documented business losses.
- A 12-hour restoration or credible-plan requirement.
- A public nationwide resilience audit of GPL’s network.
- Backup power and water-security plans at all critical GWI facilities.
- Monthly public reporting on electricity and water reliability.
- PUC enforcement, including penalties for repeated service failures.
- An independent, public investigation into the Canefield blackout and resulting water disruption.
- Accountability for senior executives, boards and responsible public officials where evidence establishes negligence or poor planning.
A country cannot call itself world class while its citizens endure darkness, heat, lost income and dry taps. The measure of leadership is not the size of a budget or the grandeur of a project. It is whether the state can guarantee the basics—and accept responsibility, quickly and publicly, when it fails.