“ Stop summarising failure—publish the Gas-to-Energy agreements”
|
🎧--- Listen To This Article Here : 👇🏽
|
592GUARDIAN♦ACCOUNTABILITY♦INTEGRITY IN JOURNALISM♦GUYANA
“ Stop summarising failure—publish the Gas-to-Energy agreements”
OPINION BY :Hem Kumar November 2026
Guyana does not need another reassuring update on the Wales Gas-to-Energy project. It needs the documents. The Government’s request to extend the final disbursement date on the US EXIM Bank’s US$527 million loan—from 1 September 2026 to 30 September 2027, with EXIM ultimately allowing until 30 December 2027—is not merely an administrative financing adjustment.
It is another public signal that a project once promised for the end of 2024 remains incomplete, while the country continues to pay for temporary power and defer the benefits citizens were promised.The Government has become expert at summarising its own difficulties: “reimbursement requests have been simplified”; “the facility’s final disbursement date has been extended”; the project is “advancing rapidly.” Those phrases conceal more than they explain. Guyanese deserve the underlying agreements, schedules, cost variations, settlement terms, and enforcement mechanisms—not a press release that asks them to trust the outcome.
A loan extension is not a success
An extension of a loan drawdown period can be reasonable in a complex infrastructure project. But when it follows repeated missed completion dates, it cannot be presented as routine progress.
EXIM approved financing to support a US joint venture involving Lindsayca and CH4 Systems, with services provided by ExxonMobil. The original contract was reported at US$759 million, with Lindsayca expected to deliver the 300 MW plant and Natural Gas Liquids facility by the end of 2024. More than two years later, the Government is still seeking additional time to complete disbursements, while promising first power from one 57 MW turbine by December 2026 and the full 300 MW by mid-2027.
That is not a minor schedule adjustment. It is a material failure of delivery, and it has consequences: rented power ships, prolonged financing costs, delayed consumer relief, and a national grid that remains dependent on stopgap capacity.
The settlement must be published
The central question is not whether the contract contains a default clause. It almost certainly does. The question is why the Government appears to have settled historical delay claims, waived historical liquidated damages, and then continued to accept shifting dates without publishing the full terms of the bargain.
The Government’s own May 2026 statement confirms that it and Lindsayca resolved disputes concerning soil stabilisation and “delay-related provisions.” It also says both parties waived historical liquidated damages, which were capped at 10% of the contract price. In plain language: the contractor’s past delay exposure was settled, even as the project remained unfinished.
That settlement may have been commercially necessary to keep the project moving. But it cannot remain a private arrangement between the Government and a contractor delivering a project financed substantially by public borrowing. The public is entitled to see:
♦The original contract and every amendment.
♦ The settlement agreement and the precise claims waived.
♦ new milestone schedule and the legal consequences of missing it.
♦ liquidated-damages rate, caps, cure periods, and termination provisions.
♦ Performance bonds, guarantees, insurance, and any parent-company support.
♦ All orders, claims, arbitration decisions, and payments made outside the original contract.
♦ The full EXIM credit agreement and all amendments, including repayment terms, fees, security, events of default, and remedies.
“Commercial confidentiality” cannot become a shield for public accountability on a project of this national importance.
“Will allow” is not accountability
The Government says that failure to meet the new milestones “will allow” it to reinstate liquidated damages. That wording should alarm every Guyanese taxpayer.
A contractor should not be rewarded with a fresh set of dates after years of delay, only for the State to retain discretion over whether consequences will follow. If the new milestones are genuine commitments, the agreement should make the remedy clear, measurable, and enforceable.
At minimum, the public should know whether missed milestones trigger:
♦ Automated liquidated damages.
♦ Withholding of milestone payments.
♦ Calls on performance security.
♦ A right to engage another contractor to complete outstanding work.
♦ Termination rights.
♦ Disbarment or exclusion from future public procurement.
If none of these remedies is automatic, or if they are subject to further negotiation, then Guyana has not solved its accountability problem. It has merely postponed it.
The cost of silence
The reported US$884 million additional cost of the delay must be independently verified and broken down. Citizens should not be asked to accept a headline number without knowing what it includes: power-ship rentals, fuel, interest, financing fees, contract variations, arbitration costs, legal fees, and lost economic value.
The Government should publish a delay-cost ledger, updated monthly. It should distinguish clearly between costs caused by the contractor, costs caused by Government decisions or site conditions, and costs that would have arisen regardless. Without that separation, the public cannot judge whether further concessions to Lindsayca are justified—or whether the State is repeatedly absorbing the price of private non-performance.
What must happen now
Parliament should not simply note the EXIM amendment. It should demand full disclosure and establish a standing public oversight process for the project.
- Table and publish every agreement. The original EPC contract, all amendments, the 2025/2026 settlement, the EXIM credit agreement, and every variation or waiver must be laid in the National Assembly and posted online.
- Publish the revised critical path. Show the exact date for each turbine, the 228 MW simple-cycle milestone, the 300 MW combined-cycle completion, NGL commissioning, gas-supply readiness, and grid-interconnection requirements.
- Appoint an independent technical auditor. It should certify progress, verify causes of delay, assess whether the revised dates are achievable, and report publicly each month.
- Make remedies enforceable. Any future missed milestone should trigger a defined financial or contractual consequence, subject only to narrowly defined force-majeure events independently verified.
- Publish the true cost of delay. Every dollar spent on rented generation, financing, claims, settlements, and variations should be itemised and attributed.
- End summary governance. The public should no longer learn about material changes through carefully worded press releases after the decisions have already been made.
The standard Guyana should set
This project was sold as transformative: cheaper electricity, greater energy security, and a major step in Guyana’s development. Those benefits remain possible, but only if the Government treats public
The issue is no longer simply whether Lindsayca can build the plant. It is whether the Government is willing to govern transparently, enforce contracts, and tell citizens the truth about what has been spent, what has been waived, and what remains at risk.
Publish the agreements. Publish the milestones. Publish the penalties. Publish the costs.
Guyana cannot afford another year of summaries.
The issue is no longer simply whether Lindsayca can build the plant. It is whether the Government is willing to govern transparently, enforce contracts, and tell citizens the truth about what has been spent, what has been waived, and what remains at risk.
Publish the agreements. Publish the milestones. Publish the penalties. Publish the costs. Guyana cannot afford another year of summaries.
<